34.5KV Electrical Reliability

Owner: US Navy
Location: Naval Station Great Lakes - Illinois
Client: Webb Electric Company
Project Type: Design-Build
Professional Services: Electrical, Instrumentation/Controls
Markets: Federal Government

The 34.5kV Electrical Reliability Project was performed at Naval Station Great Lakes in Illinois. This project was executed via a teaming effort between Bath Engineering and Webb Electric Company of Florida.

The Station receives power from two Commonwealth Edison 138kV transmission lines with two 20 MVA 138/34.5kV step-down transformers that supply two 34.5kV sub-transmission loop feeders.  The scope of work called for the improvement of reliability of the electric power system. The improvements included adding automatic loop segment sectionalizing, communications assisted relay protection, and SCADA monitoring and control to all of the existing loop segments and to a new loop segment. Bath’s design added vacuum circuit breakers at three substations resulting in each loop segment in the double sub-transmission loop having a 34.5kV breaker at each end. In its final configuration, the double 34.5kV sub-transmission loop has eight step-down substations connected in a double loop configuration using nine 34.5kV line segments.  In addition, Bath also designed new single-mode fiber optic communications links between the substations for breaker status and to control and assist schemes.

The 34.5kV Electrical Reliability project included:
  • Automatic loop segment sectionalizing of the 34.5KV sub-transmission loop34.5kV Electrical Reliability
  • Communications assisted relay protection.
  • SCADA monitoring and control to each of nine total loop segments
  • Addition of 34.5KV walk-in, protected aisle vacuum circuit breaker switchgear at three substations.
  • Single-mode fiber optic communications links between all substations connected by the 34.5kv loop segments.
  • Fiber optic communications links used by SEL 311L line-protection relays in communications assisted protection schemes.
  • Fiber optic communication links used by SEL 2030 communication processors, located at each 34.5kV substation, to communicate substation status and control to and from the Master SCADA controller.
  • Implementing relaying modifications at each of five existing 34.5kV substations by the addition of SEL 311L line protection relays, SEL 587 transformer differential relays, and SEL 587Z bus differential relays.
  • Upgrading of the existing SCADA communications system from spread spectrum radio to single-mode fiber optic cabling.
  • Installing a 30″ steel casing bore under a four lane state highway and parallel Union Pacific railroad tracks for 34.5kV and fiber optic circuits
  • Installing a new 34.5kV underground loop segment between two existing substations.
  • Rerouting and reconnecting of several other 34.5kV loop segments to improve system reliability.
  • Installing a new 34.5kV station circuit breakers at the incoming utility substation.
  • Coordinating design of the 34.5kV system for paralleling a new customer owned co-generation facility with the incoming utility lines.

To read more about Bath’s Power Engineering services, click here.